| Date | Activity | Crew | Workers | Priority | Status |
|---|---|---|---|---|---|
| 2026-03-03 | Panel array Block-D row 14-18 installation | Alpha Team | 12 | high | In Progress |
| 2026-03-03 | DC cable routing Block-C trench 7 | Electrical B | 6 | medium | In Progress |
| 2026-03-03 | Inverter pad concrete pour - INV-07 | Civil Works | 8 | high | Completed |
| 2026-03-04 | String testing Block-A rows 1-30 | QA Team | 4 | high | Scheduled |
| 2026-03-04 | Mounting structure alignment Block-E | Alpha Team | 10 | medium | Scheduled |
| 2026-03-05 | Transformer delivery & placement | Logistics | 6 | critical | Scheduled |
| 2026-03-05 | Grounding grid installation Zone 3 | Electrical A | 5 | medium | Scheduled |
| 2026-03-06 | Weather station & monitoring sensors | Instrumentation | 3 | low | Scheduled |
| Material | Required | Received | Progress | Supplier | Status | $/Unit |
|---|---|---|---|---|---|---|
| Solar Panels (Longi 580W) | 86,207 | 67,240 | 78% | Longi Green Energy | In Transit | $145 |
| Mounting Rails (4.2m) | 21,552 | 21,552 | 100% | SteelFrame Inc | Delivered | $28 |
| DC Cable (10mm2) | 250,000 | 180,000 | 72% | Polycab | Partial | $3 |
| AC Cable (185mm2) | 45,000 | 45,000 | 100% | Havells | Delivered | $18 |
| Inverters (500kW) | 8 | 6 | 75% | Sungrow | In Transit | $42,000 |
| Transformers (5MVA) | 2 | 1 | 50% | ABB | Scheduled | $185,000 |
| Combiner Boxes | 320 | 280 | 88% | Shoals Tech | Partial | $850 |
| Grounding Rod (3m) | 400 | 400 | 100% | Erico | Delivered | $45 |